Which of the following is NOT a characteristic of a high-uncertainty project?
High rates of change
Complexity inthe production process
Uncertainty in the product specifications
Clear and stable requirements

Which of the following is NOT a characteristic of a high-uncertainty project? High rates of change Complexity inthe production process Uncertainty in the product specifications Clear and stable requirements

Solution

expert verified Verificación de expertos
4.3 (223 Votos)
avatar
Bruno Elite · Tutor por 8 anos

Resposta

The characteristic that is NOT associated with a high-uncertainty project is "Clear and stable requirements." High-uncertainty projects typically involve unclear or evolving requirements, making it difficult to predict outcomes and plan effectively.